TRANSFER OF MATERIAL THROUGH HATCH SOPS


TRANSFER OF MATERIAL THROUGH HATCH SOPS


1.0   PURPOSE

To transfer the material trough proper way according to cGMP.

2.0  SCOPE

This procedure is applicable for transferring of Dispensed & In-Process Material through Material Air Lock.

3.0  RESPONSIBILITY

Ø Production Pharmacist
Ø Section Supervisor
Ø Q.A Officer

4.0   PROCEDURE

4.1).   TRANSFER OF DISPENSED MATERIAL:-

Ø Shift the material in to Material Air Lock
Ø At a time open internal door of pass though (Transfer Hatch) & shift the material into the pass through.
Ø Then close internal door & open the opposite door (Outer Door).
Ø Repeat the above steps until all the dispensed material is shifted.
Ø Then shift the dispensed material in relevant area.  

4.2).   TRANSFER OF IN-PROCESS MATERIALS:-

Ø Open the one door of pass through & shift the material into transfer hatch & then close the door of pass through.
Ø Then open the other door of pass through & pick the material & close the door of pass through.
Ø Repeat the above steps until all material is shifted.

5.0   QUALITY FORMS AND RECORDS

N/A

6.0   DISTRIBUTION

Ø  Head of Operation
Ø  Q.A Manager
Ø  Production Manager
Ø  Q.C Manager
Ø  Production Pharmacist